The US Army is asking private developers to finance, build and find customers for power plants and AI data centers on land at nine of its installations, under leases in which the service puts up no money and agrees to buy none of the output. Proposals are due January 18, 2027, according to a client alert from the law firm Holland & Knight that summarizes the solicitation.

Holland & Knight dates the request for proposals November 19, 2026, and places it under the Army's Strategic Capital Initiative. The mechanism is the enhanced use lease, an authority that lets the Army rent land it is keeping to privately financed commercial projects.

Power generation is mandatory. A developer may bid generation alone or generation with a data center, but a data center by itself will not be considered, the alert says, a condition DatacenterDynamics also reports. Each project must supply its host base with electricity within one hour of a grid outage and keep doing so for at least 14 continuous days. The Army will not evaluate a proposal that misses that threshold, and it treats the backup power as a mandatory part of the rent, paid in kind.

On the money, the law firm's reading leaves the commercial risk with the bidder. The alert says all power and data center capacity is expected to be sold to outside customers the developer must secure. In the firm's words, "the Army will not commit to buy anything from the project" and projects must be viable without any Army contribution. The Army will not allow its land to be used as security and will not provide guarantees.

Other costs land on the developer too. The selected bidder pays for the environmental review, the alert says, and must post a bond or letter of credit for decommissioning before disturbing any land. Rent is set at or above fair market value.

Lease length is shorter than in the Army's previous energy round. The new solicitation seeks a 25-year initial lease with renewal options, where a June 2026 request allowed up to 50 years and did not include data centers, according to the alert's comparison. Holland & Knight adds that the substantive lease terms are not open to negotiation.

For the data centers, the Army ranks two kinds. First come hardened, physically isolated campuses built to an intelligence community standard for Top Secret workloads. Second are hyperscale and AI or high-performance computing facilities that target a power usage effectiveness, the ratio of a site's total energy use to the energy its computing equipment uses, of 1.15 or lower. Bidders must be organized in the US and majority domestically owned and controlled.

Eligible generation includes gas turbines, reciprocating engines, fuel cells, battery storage and small modular reactors, with nuclear units capped at 500 megawatts each, the alert says. Projects must avoid drawing on aquifers and be water-neutral or better.

DatacenterDynamics names the nine sites: Blue Grass Army Depot in Kentucky, Pine Bluff Arsenal in Arkansas, Tooele Army Depot in Utah, Sierra Army Depot in California, Fort McCoy in Wisconsin, Fort Bragg in North Carolina, Fort Hood in Texas, Fort Rucker in Alabama and Joint Base Lewis-McChord in Washington. It reports parcel sizes for five of them, ranging from a single 358-acre plot at Blue Grass to three parcels totaling 903 acres at Fort Rucker. Documents for Fort McCoy, Fort Hood and Lewis-McChord were removed from the procurement notice, the publication says, which limits what is known about those sites.

A pending proposal in Congress could block such projects. Military.com reports that Senator Ruben Gallego submitted an amendment to the defense authorization bill that would prohibit new privately operated data centers on military installations, with an exception for facilities run by or for the Defense Department. The amendment has not received a vote, the outlet says. It also reports that the Army conditionally selected Carlyle and CyrusOne for data center land at two other installations in March 2026 and that neither lease has been finalized.

No bidder is named in any of the three accounts. The next dates come from the Holland & Knight alert: site tours run from November 30, 2026, through December 17, 2026, questions close on January 6, 2027, and proposals are due by 5 p.m. ET on January 18, 2027. Proposals must show market support and initial customer commitments, so the first test is whether developers can sign power and computing customers before that deadline.