A company that Data Center Dynamics identifies as an Equinix affiliate has registered plans with Texas regulators for a four-story data center in Dallas at an estimated cost of $500 million. It is the third registration in 12 months for neighboring addresses on West Mockingbird Lane.

The Texas Department of Licensing and Regulation record for the project, named DA13-1, carries a registration date of November 11, 2026. It describes new construction of a 372,443-square-foot building at 1520 West Mockingbird Lane, with work estimated to start on February 1, 2027 and finish on December 7, 2029.

Equinix's name does not appear on the record. The listed owner is DA12 LLC, with an address in Redwood City, California. Data Center Dynamics reports that the LLC shares that address with Equinix and that the contact named on the filing, Arquelle Shaw, is the company's Americas president. Equinix is a colocation provider, meaning it rents data center space and connections to other companies.

On equipment, the scope of work lists mechanical and electrical systems, 18 generators and 7 generator pads. No power capacity in megawatts is given, so the record does not show how much computing load the building is designed to carry.

Nor does it point to a customer. The tenant field reads not assigned, and the form says the private funds are not provided by a tenant. On funding, the record states: "This project is privately funded, on private land for private use."

Two earlier registrations from the same Redwood City address cover a facility called DA12 at 1550 West Mockingbird Lane. DA12-1, registered in November 2025, is a four-story, 372,517-square-foot data center with an estimated cost of $542,809,034 and a construction schedule running from February 2026 to October 2027. DA12-2 covers interior fit-out of the first and second floors of that building, estimated at $293,692,007, from September 2027 to March 2028.

Added together, the three registrations carry estimated costs of about $1.34 billion. That sum comes from the filer's own estimates on state forms. It is not a spending figure announced by Equinix.

The schedules overlap. DA13-1 is due to start about eight months before the estimated completion of DA12-1. Its construction window is also longer, at about 34 months against roughly 20 months for DA12-1, although the two buildings are nearly the same size. The records do not explain the difference.

These entries sit in the state's architectural barriers database, which tracks accessibility reviews of construction projects. They are not company announcements, and their costs and dates are estimates. DA13-1 is listed as registered, while both DA12 entries are marked review complete.

Data Center Dynamics describes the DA13 site as vacant land in an industrial area near Love Field Airport, across the street from DA12.

Neither project appears yet in the company's public listings. Equinix's Dallas page shows eight data centers in the metro, numbered DA1 through DA11, without DA12 or DA13.

For customers, the filings suggest that more Equinix space is planned in a metro where the company already operates, but they say nothing about when space could be leased or at what price. A completion estimate of December 2029 means the building would not be finished for about three years if the schedule holds.

The next marker is the February 2027 start date in the filing. Before then, the record's status could move past registration, and Equinix could add DA12 or DA13 to its Dallas listings, which may bring the first capacity figures.